Organizational and technological reliability of complex buildings with recourse supply risks modeling
https://doi.org/10.26518/2071-7296-2024-21-1-120-133
EDN: LNJLER
Abstract
Introduction. In recent days, the resources of a construction project (СP) are limited; therefore, the main tasks of managing the resource supply of construction production (RSСP) are optimal planning of resources and management of material and technical support. This includes managing the resources, supply, inventory management and distribution of resources by type of construction and installation work (CIW).
Materials and methods. For a systematic analysis of the functioning of a construction project, organizational and technological subsystems are identified that have the greatest impact on the quality and reliability of construction systems. These include construction scheduling, resource support for construction and estimates that determine the cost characteristics of construction production.
Scientific novelty. As a criterion for determining the effectiveness of the construction process, the article proposes to use the organizational and technological reliability (OTR) of complex development, taking into account resource supply. The article examines the factors influencing this criterion, as well as determines the indicators of factors and the interval values of the risk assessment of OTR. The values of the OTR indicator are obtained, which is the probability of completing the project on time, and the classification of factors affecting OTR is supplemented.
Results. Contractors and developers provide construction facilities with all necessary resources according to the technological sequence of production of the CIW, established calendar plans and construction schedules. The organisation of complete supplies of resources through enterprises and divisions of production and technological equipment, as well as production and acquisition bases will provide for the redistribution of necessary resources to fulfill the production program between the construction sites of complex development.The novelty of the study lies in the modelling of the organizational and technological reliability of complex development, taking into account the risks of resource supply.
Discussion and conclusion. To ensure successful resource provision, it is necessary to take into account the risks and take into account, within the framework of information programming, the organizational and technological reliability of the technological processes of the construction project, taking into account the specific conditions and factors of the implementation of the integrated development project.
About the Authors
A.A.R.A. Al-MsariRussian Federation
Al-Msari Ahmed Abdul Ruda Awda – Postgraduate student.
4, 2nd Krasnoarmeiskaya Str., St Petersburg, 190005
A. A. Rudenko
Russian Federation
Aleksander A. Rudenko – Dr. of Sci., Cand. of Sci., Professor of the Construction Management Department, Professor.
4, 2nd Krasnoarmeiskaya Str., St Petersburg, 190005
References
1. Belov D.B., Solov’ev S.I. Determination of the significance of differences in the results of observations of the volumes of consumed and supplied resources using statistical methods. Izvestija TulGU. Tehnicheskie nauki. 2013; 11: 110–115. (in Russ.)
2. Tsopa N.V., Khalilov A.E. Resource support of investment and construction projects. Jekonomika stroitel’stva i prirodopol’zovanija. 2022; 1–2: 82–83. (in Russ.)
3. Falah Khalaf Ali Alrubaie The identity of the economic system in Iraq between the rentier state and the developmental state February 2021 Future. Journal of Pharmaceutical Sciences. 2019; 484:12-38.
4. Saaty T. L. Relative Measurement and Its Generalization in Decision Making. Why Pairwise Comparisons are Central in Mathematics for the Measurement of Intangible Factors. The Analytic Hierarchy Network Process. RACSAM. Rev. R. Acad. Cien. Serie A. Mat. 2008; No. 102(2):251–318.
5. D’yachkova O. N., Mikhailov A. E., Yakunina G. V. (2022) Experience of assessment of the attractiveness of district parks in Saint Petersburg. Sotsiologiya Goroda [Urban Sociology], no. 3, pp. 49—63 (in Russian). DOI: 10.35211/19943520_2022_3_49
6. Belov D.B., Ignat’ev A.A., Solov’ev S.I. The problem of measurement error in commercial resource accounting (using the example of natural gas supply). Metody ocenki sootvetstvija. 2012; 9: 20–24. (in Russ.)
7. Elovoj I.A., Lebedeva I. A. Integrated logistics systems for resource delivery: (theory, methodology, organization). Minsk: Pravo i jekonomika, 2017: 467. (in Russ.)
8. Garrison, Noah and Horowitz, Kara (2012) «Looking Up: How Green Roofs and Cool Roofs Can Reduce Energy Use, Address Climate Change, and Protect Water Resources in Southern California», Natural Resources Defense Council (NRDC) Report, Emmett Center on Climate Change and the Environment, UCLA School of Law, USA. 2012: 210.
9. Nadhir Al-Ansari The Need to Develop a Building Code for Iraq September. Engineering. 2014; 6(6): p. 610-632.
10. Borisyuk N.K., Smotrina O.S. (2022) [Enterprise survival in an unstable environment ]. Intellekt. Innovatsii. Investitsii [Intellect. Innovations. Investments]. Vol. 2, pp. 24–30, https://doi.org/10.25198/2077-7175-2022-2-24.
11. Zelencov L.B. Implementation of construction projects of variable functional purpos]. Construction production. 2021;2: 26–32. (in Russ.) https://doi.org/10.54950/26585340_2021_2_26.
12. Dauletbaev R.B., Vovk B.V. Reliability of building structures of buildings and structures during their operation. Innovacii i investicii. 2019; 5: 173–177. (in Russ.)
13. Kuzovkova T.A., Kuzovkov D.V., Kuzovkov A.D. Expert-qualimetric method of integral assessment of the effectiveness of innovative projects and the application of new technologie]. Sistemy upravlenija, svjazi i bezopasnosti. 2016; 3: 23–28 (in Russ.)
14. Markin V.S., Mizya M.S. Management methods for minimizing the risks of investment and construction projects under uncertainty. Herald of Siberian Institute of Business and Information Technologies. 2020;(4):52-57. (In Russ.) https://doi.org/10.24411/2225-8264-2020-10067
15. Janani R., Rangarajan P. T., Yazhini S. A Systematic Study on Site Overhead Costs in Construction Industry. Int. J. Res. Eng. Technol. 2015; Vol. 04.No. 10: 149-151. Doi: 10.15623/ijret.2015.0410026.
Review
For citations:
Al-Msari A., Rudenko A.A. Organizational and technological reliability of complex buildings with recourse supply risks modeling. The Russian Automobile and Highway Industry Journal. 2024;21(1):120-133. (In Russ.) https://doi.org/10.26518/2071-7296-2024-21-1-120-133. EDN: LNJLER